ALDI – Reroofing Works

Burton & Haydock

Project Overview

Jupiter Construction was appointed by Aldi UK to deliver critical reroofing upgrades at two operational stores: Aldi Haydock and Aldi Burton-upon-Trent. Both projects were part of Aldi's national improvement programme, aimed at addressing long-standing roof issues while ensuring minimal disruption to trading.

Duration
12/14 weeks (each site)
Value
£590k (combined) 
Completion
September 2025
Client
Aldi UK
Reroofing Works at Aldi Burton & Aldi Haydock

Aldi Haydock

At Aldi Haydock, we carried out a full strip and reroof of the store’s pitched roof. The works involved:

  • Full perimeter scaffold installation
  • Removal of the existing roof covering
  • Installation of new  ISOLINE® LOW LINE corrugated sheets to provide a watertight barrier
  • Re-battening and installation of new concrete roof tiles
  • Upgrades to rainwater goods including gutters and downpipes

The key challenge was delivering the works while the store remained live. Jupiter implemented carefully phased working hours, client agreed methodology and safety measures to ensure no impact to trading or public access.

The project was delivered over a 12-week period, completed slightly ahead of schedule and within budget. Close collaboration with Aldi UK’s project team, contract administrators Edge, and architects from the Harris Partnership ensured seamless coordination.

Aldi Burton

The Burton-upon-Trent project followed a similar scope, with a contract period of 14 weeks. Our team installed a full scaffold perimeter while maintaining public access via a designed scaffold entrance section. Works included:

  • Removal of the pitched roof’s existing tiles
  • Installation of new  ISOLINE® LOW LINE  corrugated sheets beneath a new tiled covering
  • Eaves, ridge and verge detailing using standard junction treatments
  • Upgrades to rainwater goods (gutters and downpipes)
  • Overlay of the flat roof section with condensation risk carefully managed

Seamless coordination between Jupiter, Edge, Harris Partnership, and suppliers such as Sika ensured a smooth process, despite unforeseen conditions including outdated information on the flat roof’s insulation and drainage. Sika provided onsite inspections and detailed calculations to support specification updates.

Once again, careful planning allowed the store to remain open, with all public-facing risks fully controlled. Despite the city centre location and delivery restrictions, the project was completed on programme and within the client’s budget.

Aldi Reroofing
Aldi Reroofing

Results & Outcomes

  • Improved roof performance and weather resilience
  • Resolved persistent water ingress issues
  • Zero disruption to store operations
  • High client satisfaction
  • Projects completed ahead of programme and within budget

These two schemes reflect Jupiter Construction’s ability to plan, manage and deliver high-quality roofing refurbishments within live environments. Our ongoing collaboration with Aldi UK continues to demonstrate our commitment to excellence, safety, and delivering value to our clients.