Linkage Collage at Weelsby Hall

Grimsby

Project Overview

Jupiter Construction was appointed following a competitive tender to deliver a significant two-part redevelopment scheme for Linkage Community Trust at Weelsby Hall, Grimsby. The project comprised the refurbishment of the former Estate Office and the construction of a new Small Animal Care Unit, delivered concurrently in collaboration with Richard Morris Associates.

The Estate Office refurbishment was funded by The National Lottery Heritage Fund and the Ørsted East Coast Community Fund, while the Small Animal Care Unit was supported by the Karten Network and The Wolfson Foundation. Both facilities were designed to enhance learning and community provision, requiring careful programme management and a coordinated approach to working within a heritage environment.

Duration
Estate Office: 14 weeks
Small Animal Care Unit: 30 weeks
Value
£850K
Completion
September 2025
Client
Linkage Community Trust
linkage collage at weelsby hall, grimsby renovation 5

Client Overview

Linkage Community Trust is a well-established charity supporting people with learning disabilities and autism across Lincolnshire and Yorkshire. Their services focus on education, personal development and specialised support, with a strong emphasis on creating meaningful learning environments for students. The improvements form part of their ongoing commitment to expanding high-quality, accessible facilities.

Scope of Works and Challenges Encountered

Estate Office Refurbishment

  • Enabling and strip-out works
  • Installation of cavity drain membrane and wall tanking
  • Insulation and floor screed
  • First Fix M&E
  • Lintel lifting and associated alteration to door dimensions
  • Installation of new external doors
  • Plastering, lime render and insulation
  • Joinery works including kitchen installation
  • Second Fix M&E and sanitary ware
  • Flooring and decorations
  • Final M&E testing
  • External drainage upgrades
  • New steps and external finishes
  • Application of new render (additional scope)
  • Handrails, fencing and landscaping works

Small Animal Care Unit (New Build Extension)

  • Site establishment and groundworks
  • Revised foundation design following engineering changes
  • Superstructure build including masonry, internal blockwork and steel roof elements
  • Fixed scaffolding, roof structure and coverings
  • Installation of windows and doors
  • Underfloor heating, insulation and screeding
  • First and Second Fix M&E including lighting and sanitaryware
  • Plastering, joinery and full internal fit-out
  • Decorations and flooring
  • Air test, M&E testing and completion of internal works
  • External drainage, ramps, kerbing and hard landscaping
  • Tarmac and jet-washing prior to handover
linkage collage at weelsby hall, grimsby renovation 4linkage collage at weelsby hall, grimsby renovation 1
linkage collage at weelsby hall, grimsby renovation 3

Key Challenges

Structural and Design Changes

Both buildings required mid-project engineering adjustments — including the redesign of the foundations and unexpected lintel lifting in the Estate Office. Jupiter Construction worked collaboratively with the design team and stakeholders to develop solutions that maintained progress while minimising disruption and cost impact.

Heritage Sensitivity

The Estate Office required heritage-appropriate methods, including lime plastering and carefully managed internal repairs. Protecting the building fabric while modernising services demanded a skilled and considered approach.

Programme Coordination Across Two Concurrent Workstreams

Delivering a refurbishment and new build simultaneously on a live operational site required strict sequencing, proactive communication and clear risk management. Procore was utilised to manage documentation, quality checks and information flow.

Successes

Jupiter Construction delivered a high-quality scheme that significantly improves both student learning environments and community facility provision for Linkage Community Trust. Through strong communication, timely decision-making and effective value engineering, the team successfully navigated design changes and heritage sensitivities while maintaining programme alignment.