Green Meadows Primary Academy

Menston

Project Overview

Jupiter Construction was awarded a contract to enhance the learning environment at Green Meadows Primary Academy, situated off Bradford Road. This academy educates children aged 4-19 with a range of special educational needs (SEND) and social, emotional, and mental health (SEMH) needs. The project involves remodelling two classrooms, new WC facilities, a small group room, decorations and flooring for the existing stairwell, and a new link corridor.

Duration
6 weeks
Value
£200,000
Completion
September 2024
Client
Well Springs Academy
green meadows primary academy 6

Client Overview

Green Meadows Primary Academy is located in Guiseley on a 2-acre site surrounded by fields, with a secondary site in close proximity. The academy comprises two blocks: the main school building, built circa 1972, and a separate caretaker residence.

Scope of Works and Challenges Encountered

  1. Internal Remodelling of WC Facilities:
    • Strip out existing WC provision.
    • Set out new arrangement with walls, cubicles, and partitions.
    • Structural works for a new link corridor.
    • Creation of a new accessible WC and storeroom.
    • Alterations to the reception office layout.
    • Installation of new ceilings, sanitary provisions, doors, FF&E, and all associated M&E works.
  2. Remodelling of Classrooms:
    • Demolition of walls and making good all areas.
    • New fire door layouts.
    • Repositioning of M&E services and kitchenette.
    • Formation of interlinking group rooms.
  3. Stairwell Facelift:
    • Decoration of walls.
    • Installation of new flooring.
    • Addressing ACM flooring present in the stairwell and circulation area.
green meadows primary academy 2
green meadows primary academy 1

Challenges

The project required rapid mobilisation and coordination due to the short notice appointment, with all works needing to be completed within a strict 6-week timeframe during the school holidays. This ensured minimal disruption to the academy’s operations. Additionally, integrating new structural installations into the existing building required careful planning and execution.

Successes

Jupiter Construction successfully delivered the project within the 6-week timeframe, ensuring minimal disruption to the academy's operations. The end results were met with great satisfaction from both the Client, and the end users. The remodelling has created an enhanced learning environment, allowing freedom of movement, avoiding congestion, and providing inspiring learning spaces. Adherence to budgetary constraints and a commitment to quality were maintained throughout the project. The successful completion of this project underscores Jupiter Construction's dedication to excellence, client satisfaction, and efficient execution of construction projects.