Ainleys Depot Yard

Elland

Project Overview

During Spring 2023 Jupiter Construction successfully completed a 12-week remodel of Ainleys Depot yard and refurbishment of garage and workshop area with associated external works occurring simultaneously due to client requirements. The contract fell under the Calderdale Council Terms and Conditions.

Duration
12 weeks
Value
£200,000
Completion
April 2023
Client
Calderdale Council
ainleys depot yard remodel 3ainleys depot yard remodel 2

Client Overview

Calderdale Metropolitan Borough Council is the local authority for the Metropolitan Borough of Calderdale in West Yorkshire, England.

Scope of Works and Challenges Encountered

This project was significant in terms of the volume of connected but separate tasks, including the demolition of two existing buildings including the footings and removal of unlicensed asbestos. Installation of new fencing and gates, Groundworks to enable a new substation, associated electrical works encompassing a major M&E package. Supply and fit of new steel doors, infilling of openings utilising the masonry from the demolitions which was then rendered, where rendering was not appropriate a repointing exercise was undertaken. Internally a full floor screeding, minor roof works including guttering, decorations to floor and walls and joinery to new kitchen area, doors and work benches in the newly created section.

A key challenge with this project was the traffic management of the vehicles visiting the live public waste management site which was situated next door but egress from this site overlapped the site that the project was taking place on meaning that and at the same time there was a live Grit “Salt Bin” store that was being used to supply to Gritters throughout the works – All meaning that traffic management had to be controlled as did pedestrian access and egress.

The Team

The team involved in this project were very experienced from Contracts Management to Quantity Surveyor, Site Management and Health and Safety support, this extended to a robustly managed team of sub-contractors, Jupiter Construction prides itself on a reliable and suitably competent supply chain with a solid Pre-Construction phase built into all projects.

Successes

Jupiter Construction achieved success for the client, delivering a timely project completion whilst adhering to budgetary constraints, a value engineering exercise took place to mitigate costs for the client. A cornerstone of Jupiter Constructions methodology is the strict adherence and commitment to rigorous quality assurance inspections conducted by the Site Manager and Contracts Manager.

In summary, our successes in this project led to a further build phase on the same site helped by Jupiter Constructions comprehensive commitment to quality, timely delivery, budgetary adherence and value engineering. These principles and achievements underscore Jupiter Construction's dedication to excellence, client satisfaction, and the efficient execution of construction projects.

ainleys depot yard remodel 5